"I moved in 9 years ago and the first rain when I went to work, I was like, how do I get out of here, this road was flooded, so we've been cheering for this for a long time," Menifee resident Tami McCarthy told Patch on the day the new bridge on Bradley Road opened.
Her question about how to get out of the neighborhood sums up what Bradley Road was for years. It was a road that came with a weather condition. On a dry day it was a direct north-south link across Salt Creek. When it rained, the crossing could close and drivers had to find another way. Freedom Bridge opened to traffic on Oct. 1, 2026, and the bridge itself is only part of the change. The bigger change is that Bradley Road no longer depends on the forecast.
A road you used to plan around
The City of Menifee's own announcement says it plainly. Bradley Road at Salt Creek "regularly forced the road to close during rain events." Menifee 24/7 described the same stretch as a place where flooding "previously forced road closures and detours."
For anyone who lives near the wash, that meant two versions of the same trip. One went straight across. The other was a workaround. McCarthy told Patch that taking a detour to reach Newport Road was inconvenient, and for years it was the price of living on that side of the creek in the rainy season.
Then the workaround became the only option. To build the bridge, Bradley Road was fully closed between Rio Vista Drive and Potomac Drive for more than a year. When the city announced the closure in July 2025, it said a temporary bypass wasn't feasible and pointed drivers to alternate routes on a project map. From August 2025 until this month, the detour stopped being something you used in bad weather. It was every trip.
So the opening on Oct. 1 brought back two things. One is the direct route people lost during construction. The other is a route that holds up in weather, which Bradley Road at Salt Creek has never reliably offered.
What actually crosses Salt Creek now
According to the City of Menifee and Menifee 24/7, here is what's there:
- Length: 365 feet over Salt Creek
- Traffic lanes: one lane in each direction plus a center turn lane
- Bicycles: dedicated bike lanes
- Pedestrians: sidewalks along the bridge
- Emergency access: a route the city says will help ensure faster response times for first responders
The city lists the benefits in this order: "reliable north/south connectivity on Bradley Road during a rain event," no more motorists driving through moving water in a storm, faster emergency response, and the new bike lanes and sidewalks. Reliability in the rain comes first on that list.
Geography explains why that matters beyond one block. Menifee 24/7 describes the bridge as the connection between northern and southern Menifee over Salt Creek, and the city frames it the same way, as north-south connectivity. When that crossing closed, it didn't only inconvenience the homes beside it. It cut one of the ways the two halves of the city reach each other.
Thirteen years, three councils, fourteen months of construction
Building the bridge took about 14 months, but getting to the point of building it took more than a decade.
Milestone | When |
|---|---|
Formally added to the city's capital improvement plan | 2013 |
City announces construction is set to begin | June 2025 |
Bradley Road closure notice posted | July 23, 2025 |
Construction begins | August 2025 |
City Council renames the project Freedom Bridge | July 2026 |
Bridge opens to traffic | Oct. 1, 2026 |
Official ceremony and ribbon-cutting | Oct. 13, 2026 |
At the ceremony, Mayor Pro Tem and District 1 Councilmember Bob Karwin said the project was formally added to the capital improvement plan in 2013, though discussions started even earlier. He credited former Councilman Greg August as one of its earliest supporters. "It's gone through three different generations of City Council to get us where we are today," Karwin said, as reported by Menifee 24/7.
Construction took about 14 months, the short part of the 13 years since the project entered the city's plan. Most of the time went into planning and paying for it.
The price was $16 million, drawn from federal, state, county and local sources. The City of Menifee lists the city's Quality of Life Measure, federal funds, Riverside County Flood Control, and the Local Transportation Climate Adaptation Program. At the ribbon-cutting, Mayor Ricky Estrada thanked Congressman Ken Calvert for helping secure $5 million in federal funding, close to a third of the total. "That $5 million really pushed us over the edge to get this done," Estrada said.
Karwin also said the improvements were needed to handle the city's continued growth, not only the flooding. Public Works Director Nick Fidler recognized the contractors, engineers and utility providers. The project required moving several utility lines while keeping service running during construction.
Why it's called Freedom Bridge
Until this summer, planning documents called the project the Bradley Road Bridge over Salt Creek. The new name came from the city's Veterans and Military Families Advisory Committee, and the City Council adopted it in July.
The name shows up on the bridge itself. Banners for all six branches of the U.S. military now line the roadway to honor Menifee's veterans and military families. "I think symbolically, the name is perfect for our city," Councilman Dan Temple said at the ceremony, according to Menifee 24/7.
The bridge got two openings. The first, on Thursday, Oct. 1, had no official program. Patch reported that the road opened earlier than its scheduled 5 p.m. time, and dozens of residents came out to see it while drivers crossed honking and playing patriotic music. The formal ceremony followed on Tuesday, Oct. 13. Speeches and the ribbon-cutting came after a ceremonial drive across the bridge by the Sun City CruiZers.
The order makes sense. The bridge restores the north-south Bradley Road link between downtown Menifee and Sun City, so a Sun City car club taking the first ceremonial drive fits. When the city held its public open house on the project in 2025, it chose the Sun City Civic Association at 26850 Sun City Blvd.
On foot and on two wheels
Most of the attention went to cars, but the people who walk and ride along the wash may notice the biggest change.
The Salt Creek Trail stayed open during construction, but the city detoured a segment near Bradley Road through the surrounding neighborhood. Before construction, the problem was the same one drivers had. Nearby resident Lidia Williams told Patch that she and others use the walking path a lot, and that in bad rain it had to be closed because of flooding.
The new bridge has dedicated bike lanes and sidewalks. That makes Bradley Road over Salt Creek a raised crossing for walkers and cyclists, with no water-level question attached, which the old roadway never was. How directly you can get from the trail onto the bridge depends on where you start, so check the layout in person on your next walk.
Williams also told Patch she has seen a lot of change and growth in her three years in Menifee. She called the bridge a welcome addition and worth the investment, and she said she'd welcome more infrastructure work on roads like McCall Boulevard and Bradley Road.
The first rain will be the real test
The city has called the project complete. The bridge opened in early October, before the season that made Bradley Road unreliable in the first place. That means the first real storm will be the first time many people living near Rio Vista Drive and Potomac Drive head out in the rain without thinking about a backup route. The city's own stated goal for the project is that Bradley Road keeps carrying traffic north and south during a rain event. Until now, nobody on either side of Salt Creek could count on that.
Infrastructure like Freedom Bridge changes how a part of town works day to day, and we follow those changes closely across Menifee and Southwest Riverside County. If you'd like to talk through what the new Bradley Road crossing means for your street, your commute, or your plans, Your Home Selling Pros is here to help, in English or Spanish. Contact Us.